Build the work that disturbs the most ground first: drainage, grading, major excavation, and retaining walls. Patios, structures, planting, and lighting come after, working outward from the house. That is the order Ivy Street Design uses for backyard remodels across Denver, whether the project is built in one season or spread over several years.
Quick Summary
Build order matters because heavy work damages finished work. Excavation, grading, and wall construction bring equipment, spoil piles, and trenches into the yard. If a patio or planting bed is already in place, it gets torn up and rebuilt. Sequence protects what you have already paid for.
A landscape designer quoted by This Old House puts the drainage rule plainly: people should always improve drainage in the first stage, because fixing it later means tearing up finished landscaping. The same article says heavy-equipment work belongs in the earliest phase, such as removing dead trees or planting large shade trees, so machines do not damage areas that are already done.
Start with the work that moves the most earth: drainage, grading, major excavation, and retaining walls. The Concrete Masonry & Hardscapes Association says the most disruptive elements typically come first. Its list runs from major excavation and retaining walls to the primary patio or deck, then infrastructure for later phases.
Here is the sequence we use on Denver yards, in order:

Before digging, finish the design and call 811 so utility lines are marked. Colorado 811 says public utility locates are free and that locators mark lines within 3 business days of your request. Marks come before the first shovel, not after the first surprise.
Colorado 811 also explains the tolerance zone: the area within 18 inches of utility marks in every direction. In that zone, dig only by hand, if at all. Marks show public utility lines only. If you think private lines run through the yard, Colorado 811 says to contact a private locate company once your public locate ticket is confirmed.
This is also the time to ask whether any part of the project needs a permit. We cover the common cases in our guide to permits for backyard landscaping in Denver.
Drainage and grading come first because water decides what lasts. A patio set on poorly graded ground can shift, and a planting bed in a low spot stays soggy. Setting slopes early lets every later layer sit on ground that already drains the way the design intends.
Drainage and walls often go together. Where a yard slopes, grade changes are handled with terraces or retaining walls, and both are early-phase work. Our post on retaining wall design in Denver covers what to plan before a wall goes in.
Yes. Put in the lines for future features while the ground is open, even if the feature itself comes later. The Concrete Masonry & Hardscapes Association notes that a master plan lets a contractor install conduit, gas lines, water and drainage, and foundation support in phase one for later elements. The alternative, one of its experts says, is ripping up the yard to start over.
In practice, that means thinking now about the outdoor kitchen you may add in two years, the fire feature, the water feature, and the lighting. A conduit run under a finished patio is a small job on day one and a large one later.
The work moves outward because the space nearest the house gets the most use. This Old House calls it the main sequencing rule: always work from the house outward. Doing so means you use your investment right away, and each later room connects to something already finished.
For most Denver homes, that means the main patio or covered seating area is first, followed by cooking and fire features, then secondary gathering areas, paths, and planting. The pieces that lead out of the house and into the garden set the tone for everything past them.
Yes, if one master plan guides every phase. The Concrete Masonry & Hardscapes Association says phasing does not necessarily cost more money, and that it lets you live with each phase before committing to the next. It describes gaps of a year or two between phases on larger projects.
The catch is that a phase built without the full plan can get torn up by the next one. The same source also warns that later phases rarely end up exactly as first planned, so build in flexibility. Material choices matter too: paver shapes and colors change over time, so buying all materials up front, or planning variation on purpose, avoids a mismatch between phases.
One design carries more value than several separate ones. It also lets you compare bids from different contractors on equal terms. We go deeper on this in our guide to landscape master plan phasing in Denver.
Start the design early, then schedule construction when the ground allows it. Design, survey, and permitting work can happen before the ground thaws, which lets construction begin without delay. For a realistic view of how long each stage takes, see how long a landscape design project takes in Denver.
Ivy Street Design has designed Denver metro landscapes since 1992 and offers both design-only and design-build services. Our process starts with site analysis, moves to a 3D presentation, and includes construction observation, so the build follows the plan and the order stays intact.
The first step is a complete design based on a site analysis, followed by an 811 call for utility marks. Construction starts with drainage, grading, and the most disruptive work. Finishes such as planting come last.
No. A backyard can be built in phases as long as one master plan guides all of them. Infrastructure for later phases should go in during the first phase so nothing has to be torn up later.
Plants are the easiest thing to damage during construction. Heavy equipment, trenching, and material staging all happen earlier, so planting after that work protects both the plants and the budget.
Yes, and your contractor will expect marks before digging. Colorado 811 says public utility locates are free and marked within 3 business days. Keep marks visible for the full duration of the project.
Not necessarily. The Concrete Masonry & Hardscapes Association says phasing does not necessarily cost more. Cost goes up when phases are built without a master plan and earlier work has to be redone.
Call Ivy Street Design at (303) 320-0362 or visit ivystreetdesign.com to schedule a consultation.
Sources: Colorado 811, What You Need to Know; Concrete Masonry & Hardscapes Association, phased backyard construction; This Old House, how to design a yard in phases.